Activities

Underground Contruction

Extension of the Third line of Capital metropolitan and construction of two metro stations

The project is funded by: OP “Transport and Transport Infrastructure” 2014-2020
Budget: 75 582 000 BGN
Start date: 05 Jan 2016
End date: 30 Oct 2019
Employer: Metropoliten JSC
Contractor: Consortium „METRO CONSTRUCTION”

PROJECT FOR EXTENSION OF THE METRO IN SOFIA, THIRD METRO LINE – DEPOT "BOTEVGRADSKO SHOSE" BLVD. -  "VLADIMIR VAZOV" BLVD. - CENTRAL CITY AREA - "OVCHA KUPEL" LIVING AREA, FIRST STAGE FROM KM 4+950 TO KM 11+966.34 AS PER SPECIFIED POSITIONS

The present contract includes the design and construction of the specified position No. 3. The construction of two underground metro stations is provided (MS 6 and MS 6) and tunnel section after MS 6, which will have a length of 191,45 m. MS 6 will be constructed by open method and MS 8 and the tunnel section after MS 6 - by the new Austrian tunnel method. The length of the metro section is 1,611.05 m. The contract also requires the complete equipment of the two metro stations and the tunnel section.

Partners in the union "METRO CONSTRUCTION" are "Trace Group Hold" PLC, "Evro Alliance Tunnels" AD and "Injproekt" OOD. Duration of implementation of the project is 45 months